We are working to restore electricity by May 27- TCN to North-East Governors

We are working to restore electricity by May 27- TCN to Nort

The Transmission Company of Nigeria, TCN, has informed governors of North-East states that efforts are underway to restore electricity to the region by May 27, 2024.

According to a circular signed by the spokesperson of the commission, Ndidi Mbah, on Tuesday, TCN reported that its team is actively rebuilding the four towers that were destroyed by vandals in the region, and requested a bit of patience as the reconstruction progresses.

Mbah also mentioned that the commission has required contractors to install on-site machines to accelerate the fabrication processes of tower components, which is currently in progress. 

“The Transmission Company of Nigeria (TCN) wishes to assure the North East Governors Forum (NEGF) that we are doing everything possible in our power to ensure the restoration of power supply to the North Eastern axis of the country, as earlier indicated in our press release of 10th May 2024.

“Our team has been tirelessly working to rebuild the four towers destroyed by vandals, and we will not rest until power is restored to all the affected areas. We appeal for a little more patience, as work is truly advancing.

“To expedite the work, we have insisted that the contractor put in place on-site machines that will help increase the fabrication processes of tower members which is ongoing.

“We expect power supply to be restored by May 27, 2024, through the new 330kV transmission line, allowing Yola and Jos DisCos to offtake and distribute optimally from TCN substations,” the circular read in part.  

Related Topics

Join our Telegram platform to get news update Join Now

0 Comment(s)

See this post in...

Notice

We have selected third parties to use cookies for technical purposes as specified in the Cookie Policy. Use the “Accept All” button to consent or “Customize” button to set your cookie tracking settings